Time is one of the most critical factors in any custom light installation project. Unlike off-the-shelf decor, custom installations cannot be ordered and delivered overnight — they require design, engineering, fabrication, and logistics coordination that must be planned well in advance.
For Custom Lights used in Event Decorations, understanding the full timeline from design to delivery is essential for successful project planning. Missing a milestone can delay an entire event, while proper scheduling ensures smooth execution and avoids costly expediting fees.
This guide provides a complete timeline for custom light installations — covering each phase from initial consultation to final installation — with typical durations and key considerations for event planners.

Project Phases Overview
A typical custom light installation project progresses through six phases. Each phase has specific activities, deliverables, and typical durations.
Phase | Typical Duration | Key Activities | Deliverables |
|---|---|---|---|
Phase 1: Definition | 1–3 weeks | Brief development, site assessment | Approved project brief |
Phase 2: Design | 2–4 weeks | Concept design, engineering, approvals | Approved design and engineering drawings |
Phase 3: Fabrication | 4–10 weeks | Frame fabrication, electrical, finishing, QC | Completed components, test results |
Phase 4: Logistics | 2–6 weeks | Packaging, shipping, customs clearance | Components delivered to site |
Phase 5: Installation | 1–4 weeks | On-site assembly, commissioning | Fully installed, tested display |
Phase 6: Handover | 1–2 weeks | Final inspection, documentation, training | Accepted installation, close-out docs |
Phase 1: Definition (1–3 Weeks)
The definition phase establishes the foundation for the entire project. A well-defined brief and thorough site assessment prevent misalignment and reduce the risk of costly changes later.
Key activities:
Develop the project brief (see our Custom Light Installation Brief Template guide)
Conduct a site assessment (see our Site Assessment Checklist for Light Installations guide)
Establish budget and timeline expectations
Identify approval workflows and stakeholders
Deliverables:
Approved project brief
Budget and timeline agreement
Signed contracts
Planning considerations:
Allocate sufficient time for site assessment and requirements definition
Include all stakeholders in the definition phase
Be specific about technical requirements
Phase 2: Design (2–4 Weeks)
The design phase transforms the project brief into detailed design and engineering documentation. This phase requires close collaboration between designers, engineers, and the client.
Key activities:
Concept design and visualization
Structural engineering and load calculations
Electrical design and power planning
Material selection (see our Fabric Comparison for Custom Lanterns guide)
Design review and approval
Deliverables:
Approved concept designs
Engineering drawings
Material specifications
Electrical and structural designs
Planning considerations:
Allow 2–3 design iterations
Include technical review by engineers
Allocate time for client approvals
Consider cultural and regulatory requirements
Phase 3: Fabrication (4–10 Weeks)
Fabrication is the most time-intensive phase. It involves transforming design specifications into finished components ready for shipping.
Key activities:
Frame fabrication (cutting, welding, assembly)
Electrical installation (wiring, fixtures, testing)
Fabric cutting and pasting (see our Pasting Techniques for Custom Light Fabric guide)
Surface finishing and decoration
Quality control and testing (see our Corrosion Protection for Outdoor Light Steel Structures guide)
Packaging preparation
Deliverables:
Completed, tested components
Quality control documentation
Packaged components ready for shipping

Phase 4: Logistics (2–6 Weeks)
Logistics covers the transportation of finished components from the fabrication facility to the installation site.
Key activities:
Packaging and crating
Freight booking (air, sea, or land)
Customs clearance and documentation
Insurance coverage
Delivery coordination
Deliverables:
Components delivered to site
Customs clearance documentation
Delivery confirmation
Planning considerations:
International shipping requires 4–6 weeks (sea freight)
Air freight is faster but significantly more expensive
Customs clearance requires accurate documentation
Shipping delays are more common during peak seasons
Factor in port-to-site transportation time
Phase 5: Installation (1–4 Weeks)
Installation is the on-site assembly and commissioning of the completed components. This phase requires coordination between the installation team, venue staff, and event organizers.
Key activities:
Site preparation and staging
On-site assembly (structural, electrical, finishing)
System testing and commissioning
Adjustments and fine-tuning
Site cleanup
Deliverables:
Fully installed and tested display
Commissioning documentation
Site acceptance

Phase 6: Handover (1–2 Weeks)
The handover phase is the final step before the event. It involves formal acceptance and preparation for the event.
Key activities:
Final inspection by client
Documentation of installed configuration
Operator training (if required)
Sign-off and acceptance
Deliverables:
Acceptance certificate
Operations and maintenance documentation
Training records
Planning considerations:
Allow time for final adjustments
Ensure all documentation is complete
Train operators in advance of the event
Typical Total Duration
The total project duration for a custom light installation typically ranges from:
Project Type | Typical Total Duration | Notes |
|---|---|---|
Small project | 8–12 weeks | Simple design, local delivery, standard fabrication |
Medium project | 12–16 weeks | Custom design, regional delivery, moderate engineering |
Large project | 16–22 weeks | Full customization, international logistics, engineered structures |
These durations assume standard timelines. Expedited projects may be possible but incur additional costs.
Production Timeline and Seasonality
The timeline above assumes standard production conditions. Two field-level realities can shift the schedule significantly — both rooted in how the lantern industry operates across the calendar year.
Off-Season vs Peak Season
Lantern production follows a sharp seasonal curve. The main production window — the off-season — runs from March to September. During this window, workshops have available capacity and skilled labor is accessible. A medium-scale lantern project typically completes fabrication in 30–45 days.
From October through February, the same project enters peak season. Overseas holiday orders and Chinese New Year production overlap, and workshops are booked months in advance. Two consequences follow: lead times extend by 2–4 weeks beyond the off-season baseline, and labor cost rises sharply.
The labor cost difference is substantial. A skilled fitter (钳工) on the factory floor earns roughly RMB 240–280 per day during the off-season. In peak season, the same fitter's day rate rises to RMB 600–800. When multiple large overseas orders overlap, individual day rates can exceed RMB 2,000. For projects scheduled into this window without early booking, labor cost can effectively double.
Compressed Lead Time
A medium-scale lantern project completes standard fabrication in 30–45 days. Compress that to under 30 days and labor cost increases sharply — not linearly. Meeting the shorter deadline requires parallel shifts, expanded supervision, and expedited material procurement. The 15-day difference between 45 days and 30 days represents a step change in cost rather than a smooth reduction.
Expedited production and shipping generally add 20–50% to base cost. For projects tied to fixed event dates, early engagement is the most reliable way to avoid this premium.
Seasonal Planning Considerations
For events during peak seasons (Christmas, Lunar New Year, major festivals), additional considerations apply:
Lead times are longer: Fabricators are often booked months in advance
Shipping is slower: Freight capacity is limited during peak periods
Premiums apply: Expedited services are more expensive
Planning is essential: Early engagement is critical to secure capacity
Booking production into the off-season window where possible reduces both cost and schedule risk. For events tied to fixed peak-season dates, engaging fabricators 4–6 months in advance is the practical minimum.
Conclusion
A typical custom light installation project requires 8–22 weeks from initial consultation to final installation, depending on project complexity, location, and seasonal factors. Each phase — definition, design, fabrication, logistics, installation, and handover — requires careful planning and coordination.
Event planners should engage fabricators as early as possible to secure capacity, allow for design iterations, and avoid peak-season premium pricing. For budget planning, refer to our Custom Light Installation Cost Breakdown and Price Reference Ranges for Custom Light Projects articles.
References
DB51/T 2876-2022 – Zigong Lantern Production and Exhibition Work Behavior Requirements §6–10
DB51/T 2939-2022 – Zigong Lantern Fabrication Process General Specifications
Industry standard project timeline and project management best practices